Resource · Updated June 2026

Pay Point Evidence Checklist

Payment follows evidence, not declarations. A pay point is ready when its required artifacts exist, meet the standard, and are filed where the reviewer expects them. This checklist covers the eight pay points most milestone schedules share.

How pay points fail

Pay points rarely fail on the field work. They fail on the file: an unsigned document, an expired permit, a drawing set that does not match the permitted scope, a photo log nobody captured. The fix is an evidence inventory kept current against the deliverable checklist — not a heroic document hunt the week the invoice is due.

Pay point 1 — Package approval

  • Completed site package with maps, citations, and required exhibits
  • Customer acceptance or approval record on file
  • Open conditions from the approval recorded as tracked items

Pay point 2 — Lease execution

  • Fully executed lease with all exhibits attached
  • Owner identity verified against the executed signature block
  • Legal description and lease area exhibit consistent with the package
  • Access and utility easements documented

Pay point 3 — Zoning approval

  • Approval letter or determination on file — or documented confirmation that approval is not required
  • Conditions of approval listed as tracked items with owners
  • Hearing records retained where a hearing was required

Pay point 4 — Permits issued

  • Permit copies on file with numbers, issuance dates, and expiration dates
  • Permit conditions recorded and assigned
  • Expiration dates checked against the construction schedule

Pay point 5 — Design approval

  • Stamped drawing set on file at the approved revision
  • Redline responses resolved and recorded
  • Final for-construction set distributed and acknowledged

Pay point 6 — Construction readiness

  • NTP letter issued and on file
  • Contractor package handoff confirmed
  • Access, utilities, and permits verified ready as of the NTP date

Pay point 7 — Closeout

  • Completion notice and client acceptance documented
  • As-built drawings filed
  • Photo log complete per requirements
  • Punch-list items resolved with sign-offs
  • Inspection records retained

Pay point 8 — Invoice

  • Billable deliverables packaged per the contract's documentation requirements
  • Invoice references the PO and pay point correctly
  • Submission confirmation retained
  • Any short-pay or rejection reasons tracked to resolution

Keeping pay points honest

Two habits keep this list from decaying. First: the evidence inventory is updated when artifacts arrive, not when the pay point is due. Second: readiness is verified by the responsible party against the file — a pay point is never declared complete by the person who wants it to be complete.